Mar 17th planning commission agenda

10B - road closures

Some interesting facts about Road Events.
We can comment on the procedure at the BOS meeting on tuesday OR you can send in your suggestions via email to your supervisor of choice.

David's staff report talks about a public benefit, but only mentions money to a Non Profit in Napa County.
But what is the benefit to the Residents? Visitors? Napa County'

Also, after reading the pertinent code, I noticed 10.24.080 B, where the permit will have automatic approval if the director has not acted on the application within the time period set forth in subsection (A)......
The permit application window is 1 year in advance up to 60 days before the event, BUT the director only has 20 working days to review and approve the event. (gosh, this sounds familiar to our normal treatment). THIS sounds like it favors the applicant.

See 10.24.120 for Appealing the granted permit: THE public has only 4 working days after the approval decision to appeal the approval. WHAT, ONLY 4 DAYS. This favors the applicant and Director over the residents along the roads. And then there is noticing? How can the . residents of NC and residents along the route receive notice in 4 days? For that matter, what is the noticing requirement?

And then there is 1.20.150 violation penalties. What is the penalty?. In 6/15/04 punishment was $100 fine.